FRIZONIA has supplied the ventilation equipment of the ASP Machine House technical building (engine room of the air separation plant) for the Steel Complex currently under construction in Algeria.
In particular, there are four air supply modules and two extraction modules. They are huge equipment, which circulate a total of 145000 m3/h of filtered air. Despite the high work flow, these equipment have silencing units that attenuate the propagation of noise to the outside. This industrial steel complex will reduce imports costs in Algeria, which amount to 10 billion dollars per year. |
|